Scope of Work
- Powerline Survey
- Engineering Design
- MOU with PNG Power Limited.
- Design Review and Certification by PPL E&D Team
- Procurement of Materials and Hardware
- Materials Inspection by PPL Standards and Materials Team
- Testing by PPL Test Team
- Construction of HV and LV Lines
- Inspections by PPL Customer and Inspections Team
- Testing by PPL Test Team
- Final Inspection by PPL Team at Completion
- Energization of Line
- Commissioning of Line
Our Services
- Corridor Survey (Route Plot)
- Environmental Impact Assessment
- Social Mapping / Community Impact Study
- Engineering, Design & Documentation
- Procurement
- Construction Management
- Project Management
Project Status
At this stage, almost 97% of the works are done and is set to light-up the district on late April 2025. Detailed report will be updated once finalized.